A customer asks which bays they could install Multi-Switch Interconnect Module (MSIM). Which of the following is the source of this information?()
A customer’s new rack contains 12 x p655 servers. The customer currently has an HMC with one 128-port async adapter with a rack mounted 16-port RAN. The HMC is already attached to two pSeries p630s. What upgrades, if any, are needed to the HMC to support the new p655 servers?()
A customer is deploying a new database on a PS701 Blade in a BladeCenter H, and requires redundant network and SAN adapters. Which configuration supports the customer requirement?()
A customer is developing a custom application that involves a multistep provisioning process for a new account. There is a custom Java client application that is generating multiple JMS messages as part of the process and sending them to the WebLogic tier where they are processed. Which three steps must you take to implement the solution to allow for scalability and parallel processing of multiple simultaneous provisioning requests while ensuring messages for an individual process are not delivered out of order?()
A customer wants to run a Domino e-mail application,a Business Intelligence database,and a batch processing application on Linux.The workloads have different behaviors and do not have peaks at the same time. What is a benefit of running these applications on a Power Systems server instead of running on separate x86 servers?()
A customer’s server is experiencing slow application response due to lack of processor power. In which one of the following systems would the addition of the Expand On Demand processor upgrade feature benefit future expansion?()
A customer has just received three enterprise systems that support a total of 48 LPARs. Which installation method expedite the process?()
A customer has recently acquired an XIV system which is up and running. The next phase of theirdata center refresh is to do a non-disruptive data migration off older EMC equipment and beginmanaging their entire environment which also includes HP and HDS storage subsystems. Whatsolution should the storage specialist propose?()
A customer would like to buy a new Power 750 and attach 2 PCIe I/O drawers. What is the minimum configuration which will support this?()
You create a Web site for a customer. You need to deploy the Web site to the customers server without any of the source files for the Web site. You do not want the customer to be able to update any of the static pages on the Web site. Which tool should you use?()